Onboarding Milestone Tracker
Progress and completion status across the client implementation with Swift Digital.
Overall progress
55%6 of 11 milestones complete
- Complete
- 6
- Pending - SEED
- 3
- Pending - Swift
- 2
- Not started
- 0
Timeline
Milestone steps plotted by week — scroll horizontally to see all dates.
- 1
New Account Established
Complete3 June
- 2
Licence Activated
Complete3 June
- 3
Credits Added
Complete10,000 email credits added.
3 June
- 4
Account Subdomain
Pending - SEEDConfirm the account subdomain to be used for hosted pages.
17 JuneOverdue
- 5
Email Deliverability
Pending - SEEDConfirm the email sending domain and apply DNS records.
17 JuneOverdue
- DKIMPending - SEED
- SPFPending - SEED
- DMARCPending - SEED
- Custom Return PathPending - SEED
- 6
Brand Assets Provided
CompleteClient to provide logos, brand colours and any style guidelines for the template build.
14 July
- 7
Template Build
Pending - SEEDTemplates designed, built and provided for review. Sent for review on 21 July.
4 August
- 8
Payment Received
Complete11 June
- 9
Account Access Granted
CompletePayment required before account access can be granted.
8 July
- 10
Swift Assist
Pending - SwiftCan only be completed once templates are finalised and content provided.
18 August
- 11
Tailored Training Session
Pending - SwiftTraining will be arranged once all above steps are complete.
28 August